Project Schedule

Task Completion Date
Background reports, initial studies , base maps: Completed
Initial site surveys and baseline geomorphic monitoring Completed
Creation of base maps Completed
Watershed Assessment Report for the Upper Reaches of the Upper Truckee River (SH&G, October 2004) . Completed
Riparian Ecosystem Restoration Feasibility Report (River Run, March 2006). Completed
Monitoring and studies 2005-ongoing
First draft of conceptual planning for river and golf course. Completed
NOP NOI issued, public scoping meetings , (begin EIR EIS process) Sept-Oct 2006
Newsletter # 1 January 2007
Public workshop held (Summary of results). Feb 8-9, 2007
Newsletter # 2 Nov 2007
Additional studies conducted (incl. Economic report ) Spring-Summer 2008
Public site walks Summer 2008
Alternatives description revision/update Fall 2008
Environmental Analysis Spring–Summer 2009
News Notes update on project June 2009
Draft EIR/EIS Released to Public August 26, 2010
Public Open House September 29, 2010
Deadline for Public Comments on EIS/EIR November 4, 2010
Final EIR/EIS Issued (Response to Public/Agency Comments) September 2011
General Plan Amendment PRC Hearing January 2012
Final EIR/EIS Certified, Project Decisions (CEQA NOD, NEPA ROD) January 2012
Depending on outcome of the EIR/EIS, the following additional phases MAY take place:
Final Designs (plans and specifications). Fall 2013
Permits (regional water board, El Dorado County, California Department of Fish and Game, Tahoe Regional Planning Agency). Spring 2014
First Phase Construction 2014
Additional Phases Construction Additional 2 – 4 years